ALL UNIT COSTS

789 cards   |   Total Attempts: 182
  

Cards In This Set

Front Back
Temporary Protection (LS)
1,000.00
Dumpster (EA)
350.00
Union - Walls/doors/millwork (MD)
800.00
Non-union - Walls/doors/millwork (MD)
450.00
Remove door/frame/hardware (EA)
35.00
Remove masonry walls (SF)
3.00
Cut opening in drywall partitions (EA)
50.00
Furniture Removal (check w/ furniture vendors) (MD)
800.00
Union - Carpet or Vinyl Flooring (includes vinyl base removal) (SF)
0.65
Union - Ceramic Tile flooring (SF)
1.00
Non-union - Carpet or Vinyl Flooring (includes vinyl base removal) (SF)
0.45
Non-union - Ceramic Tile flooring (SF)
0.75
Remove Raised Flooring System (SF)
0.80
Union - Remove acoustical ceiling - tile and grid (SF)
0.65
Union - Remove acoustical ceiling tile only - grid to remain (SF)
0.35