When determining construction activity durations, lost time from the project site can be accounted for by including what factor in the equation?
Availability
Once the master activities have been broken into construction activities, you will need to use a CAS sheet for each activity. Where on the CAS sheet do you put the man-day and duration calculations?
Back page bottom
Of the following what should be put on CAS sheets?
1. Man-days 2. Tools 3. Equipment (ETC)
Which of the following is a major use of a rough level II schedule? 1. To provide an overall picture of the entire deployment 2. To coordinate the planning effort between companies 3. To provide periods where special tools are required 4. To provide material delivery dates
To coordinate the planning effort between companies
The logic network is a basic management tool. How is it used in relation to all resources that are directly related to time?
1. Controls 2. Monitors 3. Distributes 4. All of the above
Which of the following is a major use of the logic network during the planning stage?
To indicate all activities that must be accomplished
What is the general rule for creating an activity?
An activity is created for any function that uses direct labor
Resources must be tied directly to the CAS sheet and network.
True
Why is it important to do the logic network when breaking the project down into construction activities?
To ensure all items of work are included
In the logic network, what shape is used to represent activities?
A rectangular box
In the activity block, where will the activity number be inserted?
Upper left
Where in the activity block will the late finish be inserted?
Lower right
Where in the activity block will the activity description be inserted?
Upper center
What is the main objective of the forward pass computations?
To determine the duration of the project
What are lag times?
Mandatory wait times between activities